Mount Nansen Mine Remediation LP

Mount Nansen Mine.


Project Scope

Provided layout, mechanical and piping engineering services for the water treatment plant.

Location
YT, Canada
Commodities
Gold, Silver
Services Provided
CAD + Design, Multi-Discipline Engineering

The Mount Nansen Remediation LP is a joint venture between Ensero Solutions and JDS Energy & Mining Inc, who are working together as a partnership with the Little Salmon Carmacks First Nation and the Government of Canada to clean up and reclaim the abandoned Mount Nansen Mine Site.

As part of the care and maintenance activities onsite, a water treatment plant (WTP) was engineered and installed. Giffen was retained by JDS to prepare the overall layouts of the WTP, piping and instrumentation diagrams, piping material specifications, piping layouts and material take-offs.