BOMENCO Minerals Engineering Corp. (BMEC) partnered with Giffen to complete the basic engineering package for the process plant at the Terronera Project. Giffen provided multi-discipline engineering and overall plant layout.
The key responsibilities included:
- Collecting and reviewing existing drawings and documents
- General coordination between disciplines and key stakeholders
- Participating in HAZOP/Constructability/ Maintainability Design Session
- Developing overall site plot plan
- Developing process plant general arrangement drawings
- Selection of Mechanical Equipment
- Procurement Support including Technical Bid evaluations
Endeavor Silver Corp. is completing the construction of a greenfield silver and gold mine, Terronera, in Jalisco, Mexico. The Terronera Project is an underground mine with production to start in late 2024.